5 Package Deployment : 5.2 Reviewing Scheduled Tasks

The Scheduled Tasks tab (see Figure 5.8) features a legend, displaying the icons that identify the status of each task. The Manage Tasks table displays a list of tasks that are pending execution or recently completed.
C:\Users\susan\AppData\Local\Temp\vmware-susan\VMwareDnD\94ace6f7\Screen Shot 2017-06-06 at 6.14.59 AM.png
Set Show system tasks? to Yes to display system tasks; if it is set to No, only user-defined tasks are displayed. System tasks are displayed with a grey background, and may not be modified.
Highlight the name of a user-defined task and select the Edit icon to access detailed information about the selected task:
Use the Execution drop-down to view a list of the steps performed during the selected task.
The Status field lists the status of the current task.
The Enabled? switch displays Yes if the task is enabled; No if the task is disabled.
The Name field displays the name of the task.
The Agent or Server field displays the name of the agent responsible for executing the task or the server on which the task will be completed.
Expand the Execution list to review the steps within a scheduled task; to remove a task, click the Delete icon located to the left of a task's name. The task will be marked for deletion, and removed when the tab refreshes.